Weekly Status Report
Work Completed Last Week
After sitting down with our clients we’ve managed to set up accounts for all the teachers going to use the new grade book system. Everything except the google docs side of the project is ready for implication.
Work Planned for Next Week
Going to be trying to complete the google sheet as soon as possible to be able to proceed to the final stage of the project which is properly teaching all the teachers who will be using the new system.
Open Issues
Google Sheet grade book still seems to be held up in the testing area. The google sheet is easy to break.
Open Risks
If we spend too much longer on the google sheet it will push back time for the Workshop and risk going over the deadline and going over budget.
Deliverables & Milestones
Milestone | WBS | Planned | Forecasted | Actual | Status |
Phase 1 | |||||
Research of Gradebooks | Research | Oct 22-25 | Oct 23rd | Oct 22 | Completed |
Gradebook Thinkwave tested | Programmers | Oct 26 – 31 | Oct 25 | Oct 25 | Completed |
Google Sheet Created | Programmers | Nov 1-10 | Nov 8 | Nov 9 | Completed |
Google Sheet Tested | Beta Testers | Nov 11-13 | Nov 11 | Nov 11 | Completed |
Phase 2 | |||||
Setting Up Accounts | Communication Team | Nov 13-23 | Nov 20 | Nov 19 | Completed |
Deliverable | WBS | Planned | Forecasted | Actual | Status |
Presented List of Workbook Options | Research | Oct | Oct 26nd | Oct 26nd | Complete |
Completed Google Sheet | Programmers | Nov 20 | Nov 26 | Red | |
Workshop Teaching how to use Gradebook | Communication Team | Nov 26 – Dec 7 |